User's Manual Part 2
RBS 2308 and RBS 2309 User’s Guide
9 RBS Site Integration
This chapter describes how to integrate the RBS with the BSC into the GSM
network, and the tests used to verify the integration.
Integration is carried out with the RBS connected to a transmission link (PCM
or Ethernet) and in close co-operation with a BSC operator.
All results must be documented in the test record.
Preconditions at the RBS Site
This section describes the preconditions for personnel at the RBS site before
integrating the RBS.
Before starting the integration at the RBS site, ensure the following:
• The test record for Antenna System Tests has been completed
• The test record for Site Installation Tests has been completed
• If a PSTU is used in the RBS 2308, then it must be in the operational state
traffic handling and the transmission between the PSTU and the BSC
sub-node Packet Gateway (PGW), must be established
• If a PSTU is used in the RBS 2308 and the PSTU is used to synchronize
the RBS, then the PSTU must be in synchronization status synchronized
• The RBS commissioning personnel are in contact with the BSC operator
• The RBS commissioning personnel and the BSC operator have agreed
on the following parameters:
− BCCHNO parameters
− DCHNO parameters
− BSIC parameters
− Time slots (TS) used for SDCCH
Preconditions at the BSC
This section describes the preconditions for personnel at the BSC before
integrating the RBS.
Before starting the integration at the BSC, ensure the following:
• The test record for Network Element (NE) has been completed