Time slots (TS) used for SDCCH
Work Process for RBS Site Integration
This section describes the order in which to perform the integration and tests.
Each section should be completed and the results written in the test record
before moving on to the next step in the process. See Figure below.
P010244A
Bringing the RBS
into Service
Making Test Calls on
the Air Interface
Performing
Concluding Routines
Testing Transmission
Figure 69 Work Process for RBS Site Integration
The work order can be altered, or tests can be removed due to local
circumstances. However, before any such changes are made, an investigation
of the consequences must be carried out. If the work order is changed or tests
are removed, the department responsible for this manual must be notified and
agree to the changes, or the responsibility is automatically transferred to the
person making the decision.
8.1 Testing Transmission
8.1.1 Transmission Test on E1
This section describes how to test transmission, when the E1 transmission
interface is used.