User's Manual Part 3

RBS 2109 User’s Guide
8 RBS Site Integration
This chapter describes how to integrate the RBS with the BSC into the GSM
network, and the tests used to verify the integration.
Integration is carried outwith the RBS connected to a PCM link and in close
co-operation with a BSC operator.
All results must be documented in the test record.
Preconditions at the RBS Site
This section describes the preconditions for personnel at the RBS site before
integrating the RBS.
Before starting the integration at the RBS site, ensure the following:
The test record for Antenna System Tests has been completed
The test record for Site Installation Tests has been completed
The RBS commissioning personnel are in contact with the BSC operator
The RBS commissioning personnel and the BSC operator have agreed
on the following parameters:
BCCHNO parameters
DCHNO parameters
BSIC parameters
Time slots (TS) used for SDCCH
Preconditions at the BSC
This section describes the preconditions for personnel at the BSC before
integrating the RBS.
Before starting the integration at the BSC, ensure the following:
The test record for Network Element (NE) has been completed
The test record for Integration of MSC/VLR has been completed
The BSC operator is in contact with the RBS commissioning personnel
The BSC operator and the RBS commissioning personnel have agreed
upon the following parameters:
143EN/LZT 720 0090 Uen R1A 2004-09-17