User's Manual Part 2

RBS 2109 User’s Guide
P010216B
Setting the
IDB Parameters
Reading Fault Status
Switching on the RBS
Performing
Concluding Routines
Verifying AC Mains
and/or DC Power Supply
Inspecting the
Cable Connections
Testing External Alarms
Testing Fan Unit
Figure 47 Work Process for Site Installation Tests
The work order can be altered or tests can be removed due to local
circumstances, but if this is the case, an investigation of the consequences
must be carried out. If the work order is changed or tests are removed, the
department responsible for this document must be notified and agree to the
changes, or the responsibility is automatically transferred to the person making
the decision.
7.2 Inspecting Cable Connections
1. Ensure that all power switches on the MBU are switched off.
2. Check that all cables are properly connected and all connections tightened.
7.3 Checking AC Mains and DC Power Supply
This section describes how to verify that the RBS has the correct incoming AC
Mains and, where applicable, DC power.
1
02
E