User's Manual Part 2
RBS 2109 User’s Guide
6.9 Naming an SWR Measurement
This section describes how to give the measurement a unique name traceable
to the correct antenna system on the correct site.
1. Find the cell ID in the Site Installation Documentation.
2. Read the label on the jumper measured.
3. Combine the measurement type, cell ID, and label text (a unique name
with a maximum of 16 characters).
The following example illustrates these steps: Site Installation Documentation
1. The cell ID found in the Site Installation
Documentation is "SOF007_A".
2. The text on the feeder label is "Cell A: DX1".
3. The type of measurement is DTF, so the name of
the measurement is "SWRSOF007ADX1".
Example 4 Naming an SWR Measurement
6.10 Performing Concluding Routines
This section describes the actions to be taken before leaving the site, and
provides a checklist.
6.10.1 Completing Test Record
The form below is to be filled out during site work, and must be completed
before leaving the site.
95EN/LZT 720 0090 Uen R1A 2004-09-17