User's Manual Part 1

RBS 2109 User’s Guide
5 Installation of RBS
5.1 Introduction
This document describes how to install the RBS 2109.
Target Group
The target group for this instruction is personnel involved in the installation of
an RBS.
5.2 Preconditions
This section provides preconditions that must be met before starting the
installation work.
Note: Specific preconditions exist for wall and pole mounting.
Documentation
This section presents additional documents required for the installation
procedure.
Ensure that the following documents are available:
Completed and approved record prepared during site preparation
Site Installation Documentation (prepared by the Installation Engineering
department)
Standard Site Material Installation Instructions EN/LZT 720 0014
General Preconditions
Before starting site work, ensure the following:
Site access permission received
Ordered RBS, equipment, specified tools and other necessary facilities
have been delivered
Site power is available
Site Grounding Point is available
39EN/LZT 720 0090 Uen R1A 2004-09-17