7.2 Performing Final Checks
Before leaving the site, make sure that the following tasks have been
completed:
Table 3 Checklist
Check the following: OK
1.
All cables are properly routed and connected.
2.
All sunshields are properly installed.
3.
The site is clear of waste materials.
4.
The Site Installation Documentation is updated.
5.
The modified Site Installation Documentation has been handed over
to the person responsible for the site.
6.
The RBS is powered up if the surrounding temperature changes
between hot and cold and the RBS installation is not completed
within 48 hours.
8 Verifying the Installation
To verify the RBS installation, follow the instructions in the document Verifying
RBS Installations at Site.