Work Process for Site Installation Verification
This section describes the order in which to perform the tests. When the exit
criteria are fulfilled, the tester should enter the results in the test record, see
(Page 11) and return to the work process for the next step.
Note: For instructions on setting the Installation Database (IDB) parameters,
see document Setting IDB Parameters*.
P015743C
Testing Battery Back-up
Switching On the RBS
Visually Inspecting
Equipment
Figure 1 Work Process
The work order can be altered, or tests can be removed owing to local
circumstances, but if this is the case, then an investigation of the consequences
must be carried out. If the work order is changed or tests are removed then
the department responsible for this document must be notified and agree to
the changes, or responsibility is automatically transferred to the person making
the decision.