User's Manual
Table Of Contents
Ericsson Internal
INSTRUCTIONS 2 ( 14 )
/ XSNBRKI 4/1532-LZA 701 0001 Uen
EAB/ FJG/RSP ( Louise Cederlund) 2008-05-14 G
Prepared (also subject responsible if other) No.
Approved Checked Date Rev Reference
1 Introduction
This document describes the tests that must be performed to verify the
installation of the RBS cabinet. The RBS cabinet has already been tested
at the factory.
The following units are involved when testing the site installation:
• RBS main power switch, located outside the cabinet
• Distribution power switches on the Internal Distribution Module (IDM)
• Operation and Maintenance Terminal (OMT) interface and controls on
the Distribution Switch Unit (DXU)
For information about the required test equipment, tools and documents, see
Section 2 on page 4 .
Preconditions
Before starting the tests, ensure the following:
• A completed test record for Antenna System Tests is available in the
Site Installation Documentation
• A test record for Site Installation Tests at site is available
• Documents Personal Health and Safety Information and System Safety
Information have been read
• In specific markets where the RBS is supplied without software, the
software must be loaded from the OMT according to the instructions given
in the document RBS SW Update, using the alternative “New IDB created,
using the OMT, is to be used” or “The IDB on flash card is kept”.