Installation Instruction

RBS Installation Instructions
Completed and approved record prepared during site preparation
Site Installation Documentation, specific for the site (prepared by the
Installation Engineering department)
Setting IDB Parameters, 46/1543-LZA 701 0001
Verifying RBS Installations at Site, 11/1532-LZA 701 0001
General Preconditions
Before starting site work, ensure the following:
Site access permission has been received
Ordered RBS, equipment, specified tools and other necessary facilities
have been delivered
Site power is available
Transmission line from the BSC is available
If any of the above preconditions cannot be complied with, then contact the site
supervisor or person responsible for the activity that has been missed.
Additional Preconditions for Wall or Ceiling Mounted RBS
Before installing the RBS, ensure that the following preconditions are met:
The type of fasteners are suitable for the kind of material on which the
RBS is to be mounted
Vertical installation, which is important for correct cooling
100 mm free distance from top and/or bottom, if medium generates heat
75 mm free distance from top and/or bottom, if medium does not generate
heat
200 mm free distance from the sides
Note: Horizontal distance between two operational BSU is also possible
with less distance. However, the opening mechanism requires
insertion of a tool from the side of the cabinet. So, the actual
minimum horizontal distance is depending on the tool used to
open the cabinet.
If any of the above preconditions cannot be complied with, then contact the site
supervisor or person responsible for activity that has been missed.
2
41/1531-LZA 701 0001 Uen D 2008-04-23