User's Manual
Table Of Contents
- toc
- 1 Introduction
- 2 Tools and Documentation
- 3 Installation RRU-N
- Introduction
- Target Group
- 3.1 Preconditions
- 3.2 Installation Procedure
- Figure 1 Workflow for Installing the RRU-N
- 3.2.1 Unpacking and Checking the Material
- 3.2.2 Installing RRU-N on a Pole or a Mast
- 3.2.3 Installing RRU-N on a Wall
- 3.2.4 Grounding RRU-N
- 3.2.5 Connecting the 48 V DC Power
- 3.2.6 Connecting Optical Fiber Cable and Setting RRU-N Configura
- 3.2.7 Connecting Antenna Cables
- 3.2.8 Installing the Front Sunshield
- 4 Optional Installation External Splitter/Highway Function
- 5 Optional Installation External Hybrid Combining Unit (EHCU)
- 6 Performing Concluding Routines
- 7 Verifying the Installation
- tables
RBS Installation Instructions
• Jumper cables
• Optical fiber cable (for connection to Main Unit)
If any of the above preconditions cannot be complied with, contact the site
supervisor or person responsible for activity that has been missed.
3.2 Installation Procedure
This section describes the installation procedure for the RRU-N.
K000500B
Installing the Front
Sunshield
-N
Connecting EHCU
(Optional)
Connecting Antenna
Cables
Connecting the
100-250 V AC Power
Connecting the
Optical Fiber
Installing RRU-N
on a Wall
Installing RRU-N
on a Pole or a Mast
Figure 1 Workflow for Installing the RRU-N
4