User's Manual
Table Of Contents
- toc
- 1 Introduction
- 2 Tools and Documentation
- 3 Installation RRU-N
- Introduction
- Target Group
- 3.1 Preconditions
- 3.2 Installation Procedure
- Figure 1 Workflow for Installing the RRU-N
- 3.2.1 Unpacking and Checking the Material
- 3.2.2 Installing RRU-N on a Pole or a Mast
- 3.2.3 Installing RRU-N on a Wall
- 3.2.4 Grounding RRU-N
- 3.2.5 Connecting the 48 V DC Power
- 3.2.6 Connecting Optical Fiber Cable and Setting RRU-N Configura
- 3.2.7 Connecting Antenna Cables
- 3.2.8 Installing the Front Sunshield
- 4 Optional Installation External Splitter/Highway Function
- 5 Optional Installation External Hybrid Combining Unit (EHCU)
- 6 Performing Concluding Routines
- 7 Verifying the Installation
- tables
Verifying the Installation
Check the following: OK
3.
The site is clear of waste materials.
4.
The Site Installation Documentation is updated.
5.
The modified Site Installation Documentation has been
handed over to the person responsible for the site.
6.
The RBS is powered up if the surrounding temperature
changes between hot and cold and the RBS installation is
not completed within 48 hours.
7 Verifying the Installation
To verify the RBS installation, follow the instructions in the document Site
Installation Verification.
29
50/1531-LZA 701 0001 Uen PA4 2008-07-31