Specifications

Installation
clearanceS to combuStibleS:
9"
(22.9cm)
3"
(7.6cm)
3" (7.6cm)
Side Wall
Back Wall
Adjacent Wall
These dimensions are minimum clearances but it
is recommended that you ensure sufficient room
for servicing, routine cleaning and maintenance.
Side wall to unit 9 inches (22.9 cm)
Back wall to unit 3 inches (76 cm)
Corner to unit 3 inches (76 cm)
Ceiling height 60 inches (152 cm)
Alcove Maximum Depth 36 inches (91 cm)
Alcove Minimum Width 48 inches (122 cm)
Alcove Minimum Height 60 inches (152 cm)
The unit must be installed with a minimum of 6”
(152 mm) of oor protection in front of and to
the sides of the door opening.
Figure 4: M-55C-FS Clearance to Combustibles.
thermoStat inStallation:
1. Install the wall thermostat (millivolt rated thermostat
recommended, or a 12/24 Volt rated thermostat set to
millivolts) in a location that is not to close too the unit
but will effectively heat the desired area.
2. Connect the Thermostat using a 2 x 18 gauge wire
from the unit to the thermostat.
If the heat in the room becomes to great, the high limit
switch may turn the stove off and the switch will have to
be manually reset. The switch is found below the firebox
top on the hopper’s right surface.
Remove jumper
wire and install
thermostat wires here.
Figure 5: Thermostat wire placement.
leveling leg adjuStment:
The leveling legs should be adjusted for the unit to to sit level and not rock if installed on uneven
flooring.
1. Turn levelling legs until they are at the required hieghts.
2. Tighten the nut to hold the leveling leg in position.
8