4-4 Troubleshooting
UP Off No valid connection to switch stack down
connector.
1. Make sure the switch connected to the
stack down connector is powered on.
2. Replace cable with a known good one.
3. If the problem still exists, contact
Enterasys Networks for technical
support.
Green Solid. Valid connection to switch stack down
connector.
Blinking. Information is being transferred via the
high-speed stacking cable.
None.
Manager Off Switch is operating as a Member in the stack. None.
Green Solid. Switch is operating as the Manager of the
stack.
None.
RPS Off RPS not in use.
Internal power supply failure.
None.
If an RPS is connected to the switch, it
should be providing power. Perform the
following:
1. Ensure the RPS is powered on.
2. Ensure that the AC power cord to the
RPS is plugged in correctly and that
there is power at the AC power source.
3. Replace the power cord with a known
good one.
4. Ensure the DC power cord from the
RPS to the switch is plugged in
correctly.
5. If the problem persists, contact
Enterasys Networks for technical
support.
Amber Solid. The switch internal power supply failed,
and the RPS is providing the proper power to the
switch.
None.
Table 4-3 LANVIEW LEDs (continued)
LED Color State Recommended Action