Component Guide
Planning an Ensemble Technology System – North America
5 © 2020 Enphase Energy Inc. All rights reserved. December 8, 2020
Partial Home (Subpanel) Backup – Enpower Smart Switch and a Backup Subpanel Installed on the Load Side
of the Main Load Panel
The Enpower smart switch can also be installed on the load side of the exiting main load panel or service equipment.
This configuration can be used when the Ensemble technology system is configured to provide backup to a number
of pre-selected load circuits. This configuration is recommended when Encharge storage systems with smaller energy
and power capacity and some basic load backup is desired by the customer, or when existing constraints prevent
main panel backup or other installation methods. Figure 4 below shows an example of a partial home (subpanel)
backup configuration for an IQ-Series microinverters based system while Figure 5 shows the same for M-Series
microinverter based system.
Figure 4: Always-On Ensemble technology system with partial home (subpanel) backup for IQ-Series microinverters.
Enpower is installed on the load side of the main load panel with select loads backed up in a backup subpanel.
Figure 5: Always-On Ensemble technology system with partial home (subpanel) backup for M-Series microinverters.
Enpower is installed on the load side of the main load panel with select loads backed up in a backup subpanel.