Install Manual
INSTALLATION
Plan a location for the IQ
TM
Batteries
The IQ
TM
Battery housing is NEMA type 3R and can be installed indoors
or outdoors. The terminal blocks accepts copper conductors of No. 14 - 8
AWG.
A ) Following local standards, choose a well-ventilated location where
the ambient temperature and humidity are within -15° C to 55° C
(5° F to 131° F) and 5% to 100% RH, non-condensing, preferably
out of direct sunlight. The optimum ambient temperature range
for installation location is 0º C to 30º C (32º F to 86º F). Provide
smoke alarms in the residence in accordance with building, re and
installation codes.
B ) Ensure that the mounting location can sustain the total weight
of the IQ
TM
Batteries and mounting bracket. Total weight for the
IQ
TM
Battery 3T, including the IQ
TM
Battery base unit, cover and
wall mount bracket, is 48.8 kg (107.6 lbs). Total weight for the IQ
TM
Battery 10T, including the three IQ
TM
Battery base units, cover, and
wall mount bracket, is 152.1 kg (335.3 lbs).
* WARNING: The installer should install blocking between studs
to ensure that no single stud carries the entire weight load of the
IQ
TM
Batteries.
C ) Plan the mounting location to be at least 15cm (six inches) off the
ground and 15cm (six inches) from the ceiling for IQ
TM
Battery 3T
and IQ
TM
Battery 10T.
NOTE: Wherever local codes allow a smaller separation distance
for Energy Storage installations, the minimum spacing around IQ
TM
Battery 10T MUST be at least six inches from the top, bottom, left,
and right side of the product.
Keep the IQ
TM
Battery away from falling or moving objects, including
motor vehicles.
* WARNING: If mounted in the path of a motor vehicle, we
recommend a mounting height that is 91 cm (thirty-six inches)
minimum above the oor.
D ) Ensure that there are no pipes or electrical wires where you plan to drill.
E ) Plan to maintain at least 91cm (thirty-six inches) of clearance in
front of each IQ
TM
Battery.
F ) Consider the dimensions of the IQ
TM
Batteries, easy access, height,
and length of cable when selecting the location.
G ) Select a location where you can interconnect to the Enphase IQ
TM
System Controller.
H ) Follow all local standards and restrictions set forth by AHJ
(Authority Having Jurisdiction).
I ) Up to two IQ
TM
Battery 10T (or six IQ
TM
Battery 3T) units can be daisy
chained on a single branch circuit. For installations with more than
this number of units, there must be a separate load center, subpanel,
or circuit combiner with over current protection to combine the
daisy chained circuits, and you must run only one circuit for all the
IQ
TM
Battery units to the IQ
TM
System Controller (or to Enphase IQ
TM
Combiner for grid-tied-only installations). You must select proper
conductors and circuit breakers for these circuits according to local
codes, standards, and other applicable requirements. IQ
TM
System
Controller supports up to a maximum of 80 A breaker for IQ
TM
Battery connection circuit.
The subpanel could be a small, two circuit box with circuit breakers.
The circuit breakers in the box would have to be suitable for
back-feeding, per NEC 408.36(D).
Select the right size subpanel and breakers based on the number
of IQ
TM
Battery units being installed. Up to four IQ
TM
Battery 10Ts or
twelve IQ
TM
Battery 3Ts can be safely connected to 80A load center.
To do this, you must purchase an off-the-shelf subpanel and install
as shown in the image in next column.
J ) The maximum conductor size for IQ
TM
Battery 3T and IQ
TM
Battery
10T is 8 AWG and the maximum breaker rating with this conductor
size is 40 A.
1
Install the AC disconnect
Following all local codes and standards:
A ) Install an AC disconnect that can break the maximum rated current
of the branch circuit under load. The AC disconnect must be readily
accessible and located within line-of-sight of IQ
TM
Battery, per NEC
2017 706.7(A).
B ) Each IQ
TM
Battery unit is suitable for use with up to No. 8 AWG wires
on a maximum 40 A branch circuit. If more than 32 A of IQ
TM
Batteries
(corresponding to a 40 A branch circuit) are installed, a separate
subpanel must be installed between the IQ
TM
Battery units and IQ
TM
System Controller to combine the IQ
TM
System Controller circuits
together. All circuit breakers in the subpanel must be suitable for
back-feeding, per NEC 408.36(D).
C ) Verify that AC voltage at the site is within range: single-phase L1 to L2
voltage must measure between 211 and 264 VAC, while L-N should
measure between 106 and 132 VAC.
2
Prepare to install the wall-mount bracket
A ) Make sure that the planned position for the wall-mount bracket
meets clearance requirements as shown. The image depicts a
single-width bracket for the IQ
TM
Battery 3T, but clearances and
requirements are the same when installing a triple-width bracket for
the IQ
TM
Battery 10T.
B ) Ensure that the mounting location can sustain the weight of the
IQ
TM
Batteries and mounting bracket. Total weight for the IQ
TM
Battery 3T including the mounting brackets and cover is 48.8 kg
(107.6 lbs), while the total weight for IQ
TM
Battery 10T including
the mounting bracket and cover add up to 152.1 kg (335.3 lbs).
C ) Starting at installation position closest to the power source, mark a
level line on the wall as a guide.
* WARNING! Multiple risks. Make sure not to drill or attach into
electric wiring or pipes that are in the wall!
3
Mounting on vertical stud
IQ
TM
Battery 3T
NOTE: The above shown image is just for reference. Use other slots
on the wall mount if additional xing is required for stability (To be
assessed by the installer).
Wood stud
* WARNING: Parallel power production sources only. Do not connect
load circuits.