- Audience
- Table of Contents
- SAFETY
- The Enphase IQ Envoy
- Installation Planning and Preparation
- Review the following pre-installation checks before you install the IQ Envoy.
- To install the production CT
- Installing the IQ Envoy – Part 1
- Installing the IQ Envoy – Part 2
- Use one of the following methods to detect devices (Enphase Microinverters and/or Enphase Batteries).
- IQ Envoy Operation
- You can track system installation progress with the Enphase Installer Toolkit mobile app.
- Connecting to IQ Envoy
- Once your mobile device and the Envoy are on the same LAN, you can connect to the IQ Envoy.
- Refer to enphase.com/installer-toolkit/ for more information on the Enphase Installer Toolkit.
- Select Diagnostic Tools to ping the Envoy, check network connectivity, and check the network route.
- Troubleshooting
- The following sections describe possible problems and solutions.
- Troubleshoot power line communication issues as follows.
- This means that communications from other Envoy(s) have been detected. To prevent this issue:
- Check for the following conditions.
- If Enphase Customer Support authorizes an IQ Envoy replacement (RMA), perform the following steps.
- Technical Data
IQ Envoy Installation and Operation
© 2017 Enphase Energy Inc. 141-00039 Rev 01
9
Metering Considerations
The IQ Envoy includes a production CT and you may order two consumption CTs for consumption
monitoring. When installing CTs:
• Do not install the CTs in a panel where they exceed 75% of the wiring space of any cross-
sectional area within the panel, or refer to local standards for guidance.
To install the production CT
• Ensure there is sufficient room to install the production CT around line 1 of the solar PV
disconnect.
To install consumption CTs (order CT-200-SPLIT separately)
• For net consumption metering, ensure there is sufficient room to install both CTs around lines 1
and 2 from the main feeds.
• For total consumption metering, ensure there is sufficient room to install the CTs around the
lines that feed the consumption circuit.
Box Contents
Check the shipping box for the following items:
• Enphase IQ Envoy (look for the orange IQ logo)
• Solid-core production metering CT
• Length of DIN rail for mounting
• Ferrite bead to attach to your Ethernet Cable, if used
• Enphase IQ Envoy Quick Install Guide
Required Items
Install the IQ Envoy in a NRTL certified NEMA type 3R (or better) enclosure with conduit attachment
when installing outdoors. Do not drill holes on the top of the enclosure or anywhere that allows moisture
ingress. Metallic enclosures may impair Wi-Fi signal strength. Use an appropriately rated enclosure if
installing indoors.
Optional Items
Make sure you have the following optional items, if needed:
• If you plan to do consumption metering, you need two consumption metering split-core CTs
(order two CTs: Enphase CT-200-SPLIT)
• Decide which option to use for the Internet connection:
• Enphase Mobile Connect modem [order Enphase CELLMODEM-01 (3G) or
CELLMODEM-03 (4G)]
• Ethernet over power line communication (PLC) bridge with Ethernet cables (order
Enphase EPLC-01)
• Ethernet cable [802.3, Cat5E or Cat6, unshielded twisted pair (UTP)]. Do not use
shielded twisted pair (STP) cable.