Envoy IQ Installation

Table Of Contents
IQ Envoy Installation and Operation
© 2017 Enphase Energy Inc. 141-00039 Rev 01
13
2. Provide a Power Connection
When you hard-wire the IQ Envoy, you must install it in a ventilated, NRTL certified NEMA type 3R-rated (or
better) enclosure with conduit attachment.
The IQ Envoy uses terminal blocks for power and metering connections. You must install one solid-core
current transformer (CT) for revenue-grade production metering. Consumption monitoring is optional and
requires that you order and install two additional split-core CTs. Use a protected route in conduit for the CT
wires from the main load center to the IQ Envoy. The consumption CT leads are 13 feet long. If you need to
extend the leads, refer to page 16. Do not extend the leads of the production CT.
-
 -
 
 
 
-