Enphase Ensemble Technology System Planning Tech Brief
Planning an Ensemble Technology System – North America 
9  © 2019 Enphase Energy Inc. All rights reserved.  December 17, 2019 
Load breaker installed in the Enpower smart switch 
If there is an existing service equipment such as an existing fusible disconnect on the line-side of Enpower, a main 
breaker may not be required on the line-side input of Enpower smart switch. However, a load breaker may still be 
required. Size the load breaker with the same rating as the system over current protection device for the whole home 
(main panel) backup configuration. For example, if there is an existing 200 A meter disconnect combo feeding a main 
lug panel board, Enpower smart switch would be installed with a 200 A rated Eaton CSR2200N (Enphase SKU: BRK-
200A-2P-240V) as a load breaker inside Enpower smart switch. 
Main breaker installed in the Enpower smart switch 
For the whole home (main panel) backup configuration, if the service rating is less than 200 A, a load breaker may 
not be required. For example, a 100 A service has DER over current protection totaling less than 100A. In this case, 
Enpower smart switch would be installed with a 100 A rated Eaton CSR2100N (BRK-100A-2P-240V) as a main 
breaker on the line-side of the main load panel. Ensure that the sum of load and DER breakers does not exceed 200 
A rating of the busbar and Enpower smart switch load conductors are rated appropriately. 
Enpower smart switch without main or load breakers installed 
When Enpower smart switch is installed on the load side of the service equipment disconnect means, main and load 
breakers may not need to be installed in the Enpower. For example, an Enpower smart switch is installed with total of 
40 A of DER over current protection and that is back feeding a 200 A main breaker load center. In this case, it 
necessary to install main or load breakers in the Enpower smart switch. Ensure that sum of the load and DER over 
current protection is less than 200 A and that conductors are sized to comply with 2017 NEC 705.12(B)(2)(1). 
Encharge storage system, IQ combiner or generator (future) breakers 
When connecting Encharge storage system, IQ combiner or generator to the Enpower smart switch, use one of the 
following circuit breakers depending on system requirements. 
Model Number 
Description 
Shipment Contents 
BRK-80A-2P-240V 
Circuit breaker, 2-pole, 80A, 10kAIC, BR280 for Enpower 
One box of one unit 
BRK-60A-2P-240V 
Circuit breaker, 2-pole, 60A, 10kAIC, BR260 for Enpower 
One box of one unit 
BRK-40A-2P-240V 
Circuit breaker, 2-pole, 40A, 10kAIC, BR240 for Enpower 
One box of one unit 
BRK-30A-2P-240V 
Circuit breaker, 2-pole, 30A, 10kAIC, BR230 for Enpower 
One box of one unit 
BRK-20A-2P-240V 
Circuit breaker, 2-pole, 20A, 10kAIC, BR220 for Enpower 
One box of one unit 
Encharge and generator breakers may require a BRHDK125 hold down kit in accordance with 408.36(D) as 
referenced in NEC 710.15(E). This hold down is not required for the IQ combiner circuits with IQ 6/IQ 7 microinverters 
since these inverters are still interactive inverters and are permitted to omit the additional fastener 2017 NEC 
705.12(B)(5). This aligns with the AC coupled multimode system diagram, Figure 1, in 2017 NEC Figure 690.1(b), 
which shows both an interactive and multimode inverter. Encharge storage system includes the multimode inverters 
forming an intentional local EPS island, and IQ 6/IQ 7 microinverters are utility interactive inverters.  
Generator interface 
The Enpower smart switch includes a 60 A generator connection for qualified generators. This document does not 
address this function, as the software functionality is not yet released. Enpower smart switch does not support 
integration with third party automatic transfer switches (ATS) for the interconnection of generators. Third party 
transfer switches and unqualified generators may be connected on the load side of Enpower smart switch in 
compliance with NEC 705.2, and requires isolating the Enphase DER equipment from the electrical system powered 
by unqualified generators. Such third-party transfer switches and accompanying generators cannot operate at the 
same time as Encharge storage systems and charge them. 










