5.6 Commissioning the system
Warning: Connection of the AC bus extension to the Mains Utility Grid must only be performed
by a qualified electrician. Under no circumstances should anyone other than a qualified
electrician attempt to connect the AC Bus extension to the utility mains grid. Failure to heed
this warning may result in electrical shock and death.
Attention: It is the responsibility of the installer/electrician to install all relevant apparatus and
to grid connect the solar photovoltaic installation in accordance with the regional/national
electrical codes regulations of installation country.
Attention: It is the responsibility of the qualified electrician to perform all relevant safety
checks before fully commissioning the solar photovoltaic installation.
1. The electrician switches on the system, the system is now feeding renewable energy into the
utility grid, generating a return on investment.