User's Manual

Table Of Contents
SYSTEM DESCRIPTION, INSTALLATION, AND MAINTENANCE MANUAL
eNfusion® HSD-440 Mark 2 Terminal
23-15-30 3-1
3 JUN 10
INSTALLATION
This section provides procedures to install HSD-440 Mark 2 Terminals on an aircraft, including the
following sections:
Advisories
Pre-Installation Inspection
Mechanical Installation
Electrical Installation
Passive Intermodulation (PIM) Test
Installation and Engineering Diagrams
1. Advisories
Read the safety advisories in the Introduction section on page INTRO–6 of this manual before
you begin installing the terminal.
2. Pre-Installation Inspection
Inspect all parts before you install any HSD-440 Mark 2 Terminal, to make sure that no damage
occurred during shipping.
A. Unpacking and Inspecting Equipment
Unpack the HSD-440 Mark 2 Terminals from the shipping containers.
Verify that the part number displayed on the shipping box and equipment component
matches the model and part number ordered. If components are missing from the
shipment, contact the supplier or Honeywell Product Support immediately and report
the problem.
Visually inspect the terminal for any shipping damage. If any shipping damage has
occurred, contact the shipping carrier immediately and report the problem.
Check the HSD-440 Mark 2 Terminal connectors for corrosion and damage. If
damage is noted, do not apply power to the terminal. Contact the supplier or
Honeywell Product Support immediately to report the problem.
B. Cabling Notes
Before proceeding with the installation of the HSD-440 Mark 2 Terminal, read all cabling
notes provided on the HSD-440 Mark 2 Terminal Interconnection and Contact
Assignment drawings at the end of this section.