Installation Instructions
Installation Instructions Section 5876
Spec. No. 582140000 (Models 802
NLDB, 802NLEB and 802NL-B) Issue AT, April 26, 2013
Chapter 1. General Information and Installation Checklist Page 1-1
This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy
Systems, North America, Inc. Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited.
CHAPTER 1
GENERAL INFORMATION AND
INSTALLATION CHECKLIST
TABLE OF CONTENTS
Preface .................................................................................................................... 1-1
Installation Acceptance Checklist ............................................................................ 1-1
PREFACE
This document (Section 5876) provides Installation Instructions for NetSure™ Power
System Model 802
NLDB (208V Input Power/Distribution and Power Only Bays), 802NLEB
(480V Input Power/Distribution and Power Only Bays) and 802
NL-B (Distribution Only
Bay); Spec. No. 582140000. For a condensed version of these instructions, refer to the
Installation Guide (Section 5957) located in the separate INSTALLATION MANUAL.
For User Instructions, refer to Section 5877 provided on the CD (Electronic
Documentation Package) furnished with your system.
Refer to SAG582140000 (System Application Guide) for additional information. The SAG
can be accessed via the CD (Electronic Documentation Package) furnished with your
system.
For a color MCA Menu Tree, refer to Section 5886. Section 5886 is provided in the
separate INSTALLATION MANUAL and the CD CARRIER MANUAL (it is also provided
on the CD).
Your Power System may contain an optional LMS Monitoring System, refer to Section
5879 (LMS1000 Installation Instructions) and Section 5847 (LMS1000 User Instructions)
provided on the CD (Electronic Documentation Package) furnished with your system.
INSTALLATION ACCEPTANCE CHECKLIST
Provided below is an Installation Acceptance Checklist. This checklist helps ensure
proper installation and initial operation of the system. As the procedures presented in
Chapters 2 through 5 of this document are completed, check the appropriate box on this
list. If the procedure is not required to be performed for your installation site, also check
the box in this list to indicate that the procedure was read. When installation is done,
ensure that each block in this list has been checked. Some of these procedures may
have been factory performed for you.
Note: The system is not powered up until the end of this checklist.
Note: Some of these procedures may have been performed at the factory for you.
Chapter 2. Placing the Bays and Installing Internal/External Busbars
Bays (and PDSC if furnished) Bolted Together (if required) and Mounted to Floor
Bay-to-Bay Busbar Links Installed (if required)
PDSC (if furnished) AC Input Connectors Connected to Power/Distribution Bay
External Top-Mount Busbar Assemblies Installed (if furnished)