Installation Guide
Section 5957 Installation Guide
Issue AM, March 26, 2014 Spec. No. 582140000 (Models 802NLDB, 802NLEB and 802NL-B)
Page 2
This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy
Systems, North America, Inc. Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited.
Refer to drawing 031110100 for lug crimping information. Refer to drawings 031110200
and 031110300 for additional lug information. These are located in the Installation
Manual.
All wiring and branch circuit protection should follow the current edition of the American
National Standards Institute (ANSI) approved National Fire Protection Association's
(NFPA) National Electrical Code (NEC), and applicable local codes. For operation in
countries where the NEC is not recognized, follow applicable codes. For field wiring, use
wires suitable for at least 75°C.
Installation Acceptance Checklist
Placing the Bays and Installing Internal/External Busbars
Bays (and PDSC if furnished) Bolted Together (if required) and Mounted to Floor
Bay-to-Bay Busbar Links Installed (if required)
PDSC (if furnished) AC Input Connectors Connected to Power/Distribution Bay
External Top-Mount Busbar Assemblies Installed (if furnished)
Installing Distribution Devices, MCA Relay
Circuit Cards, and MCA I/O Circuit Cards
Distribution Fuses and Circuit Breakers Installed
Distribution Lug Adapter Plates Installed
MCA Customer Alarm Relay Circuit Card(s) Installed (if required)
MCA I/O Circuit Card(s) Installed (if required)
Making Electrical Connections
MCA Network Bay Interconnections Made
MCA Battery Charge Digital Temperature Compensation Probe Mounted and
Connected (if furnished)
MCA External Alarm, Reference, and Control Connections Made
Connections Made to all MCA I/O Circuit Cards Installed
LMS Local Port Connection Made (If Required)
Bay(s) Frame Grounding Connections Made
Bay(s) Load Connections Made
Bay(s) AC Input and AC Input Ground Connections Made
Battery Connections Made
All Shields and Cover Panels in Place
Installing the Rectifiers and Setting Switch Options
Rectifiers Installed
MCA and Router Circuit Cards Switches Set
Distribution Bus Monitoring Circuit Cards Jumper Set