3.1.3. Step 3. Route Cable away from Electrical Interference
Network cables should enter the electrical enclosures and the
bottom or lowest point (on 320A systems, this is near the
transformer end and normally in a counter clockwise direction
to the topside of the TBM). Never install network cable in the
same conduit with power conductors. Never route the network
cable through the high voltage contactor area. On 320A
systems, the cable should never lie across the TBM or hinder
the protective cover of the TBM. Always use the shortest
distance and keep access cable to a minimum.
See Figure 3-1
3.1.4. Step 4. Observe Polarity and Network
Grounding
Each network connection is polarized + and - on wiring
diagrams. Always use consistency in wiring and the use of
wire colors to track polarity. The cable shield (or “drain wire”)
must be connected to the designated “shield” terminal at each
port of each actuator. The shield must be connected to earth
ground at only one point. Some networks require a jumper
between the shield connections on ports A & B of the actuator
to carry the shielding through the network. The shield
connection of each actuator is isolated from earth ground.
Do not allow the shield to touch other circuits or the metal enclosure.
3.1.5. Step 5. Wire Preparation and Connections
Screw terminal connections on the TBM and in the TEC2000 terminal chamber have wire clamps,
which will accept conductors with out terminals. Wire terminals may be applied if desired but are not
required. Strip conductor insulation back 3/8” when connecting directly to the TBM screw terminals. Do
not allow wire clippings to fall on the TBM or into the enclosure.
Protect the conductors and shield to prevent them from contacting any other circuits or earth ground.
Use plastic electrical tape or heat shrink tubing to prevent bare conductors from contacting other
circuits or earth ground.
See Figure 3-1
3.1.6. Step 6. Test Network
Use EIM’s Configuration and Control Utility (CCU) to test the network prior to connecting to the host or
network master. The CCU is a Windows application, which will run on a laptop. Use a RS232 to RS485
adapter or EIM’s Network Interface Unit (NIU) to connect the laptop to the network. Test each actuator,
one at a time, to determine that all network connections are good and each actuator is functional via the
network in remote.
Figure 3-1
Correct termination of the Network
to a Controlinc 320A Actuator