Installation Manual

NetSure™ LMS Data Processing Unit
Installation Instructions, Section 5879 (Issue BA, April 7, 2014)
Spec. No: 58650500, 586505500 Code: Section 5879
Model No: LMS1000 Issue BA, April 7, 2014
Connections Made to all Eight Input Binary Circuit Cards
Installed
Connections Made to all Four Output (Form-C) Relay
Circuit Cards Installed
Connections Made to all Eight Input Temperature Circuit
Cards Installed
Optional Expansion Assembly(s) (if furnished)
Interconnected to Customer Equipment
All 586505000/586505500 Expansion Cabinets,
582140000/582140001/582126100 Secondary Bays,
and/or 586505000/586505500 Expansion Assemblies (if
furnished) Interconnected into LMS1000 Network
Energy Management Connections Made, if required
Sequential Start Connections Made, if required
System Powered Up and Checked
Configuring LMS1000
System Configured
Installing LMS1000
Installing the LMS1000 Display Option
Refer to Section 5942 or Section 5943 to field install an LMS1000
Display option. These are provided in the LMS1000 Installation
Manual, and on the CD provided with your system documentation.
The option is factory installed if ordered with the system.
Mounting the 586505000/586505500 Main Cabinet
and Expansion Cabinet(s) (if furnished)
The installer should be familiar with the installation requirements
and technique to be used in mounting the cabinet(s).
Note that Spec. Nos. 582140000, 582140001, and 582126100
Power Systems do not use the LMS1000 Cabinets. The LMS is
factory integrated into the Power Systems.
Mounting
The cabinet(s) is to be mounted in a relay rack with 1 or 1-3/4 inch
multiple drilling.
586505000 Lists 1 and 6: The cabinet(s) is provided with
reversible mounting angles to allow mounting in a 19 inch or 23
inch wide relay rack. The mounting angles may also be positioned
for flush front mounting, 5-inch front projection mounting, or
6-inch front projection mounting. If necessary, remove and
reposition the reversible mounting angles to meet your
requirements.
586505000 and 586505500 Lists 2 and 7: The cabinet(s) is to be
mounted in a 23 inch wide relay rack. The mounting angles may
also be positioned for flush front mounting, 5-inch front projection
mounting, or 6-inch front projection mounting. If necessary,
remove and reposition the reversible mounting angles to meet
your requirements.
Note:
A removable label is provided on the front panel of the Main
Cabinet. This allows the user to write the functions of the
programmable LEDs, if desired.
Grounding Connection
Main and Expansion Cabinets: The earth ground connection to the
cabinet is made via an external connection brought to the outside
of the cabinet. Refer to "MAKING ELECTRICAL CONNECTIONS" in
this section for details.
Relay Rack: Refer to the National Electrical Code, applicable local
codes, and your specific site requirements.
Mounting the Optional Expansion Assembly(s) (if
furnished)
The installer should be familiar with the installation requirements
and technique to be used in mounting the assembly(s).
Mounting
The assembly(s) is to be mounted in customer equipment, as
required.
The assembly(s) is provided with a back sheetmetal panel with
mounting holes. Mount the assembly to a suitable surface. Refer
to SAG586505000/SAG586505500 for mounting hole dimensions.
The SAG can be accessed via the CD (Electronic Documentation
Package) furnished with your system.
Grounding Connection
The earth ground connection to the assembly(s) is to be made
with the hardware used to mount to assembly(s). This requires the
use of a ground washer with the assembly(s) mounting hardware.
A ground washer is an internal-external tooth, dish-type lock
washer.
Installing Circuit Cards
Circuit cards may have been factory installed for you.
The 586505000/586505500 cabinet(s) should be unpacked and
mounted prior to unpacking and installing the circuit cards. Note
that Spec. Nos. 582140000, 582140001, and 582126100 Power
Systems do not use the LMS1000 Cabinets. The LMS is factory
integrated into the Power Systems.