User manual

Installing a Liebert iCOM Unit-to-Unit Network
83 Liebert
®
iCOM
®
for Liebert DSE
5.0 INSTALLING A LIEBERT ICOM UNIT-TO-UNIT NETWORK
Connecting multiple Liebert iCOM-controlled cooling units in an Ethernet Unit-to-Unit (U2U)
network enables the units to work together to achieve efficient cooling and humidity control of the
conditioned space. Networking enables setting up the cooling units to exchange data for various
modes of operation:
Teamwork
Lead/Lag-Standby
Rotation
Cascade
However the cooling units are set up, a large display may be used to control and view the operational
status of individual units or of the entire system.
5.1 Placement of Cooling Units
Refer to the cooling unit product manuals for details on installation. Also consider these factors when
planning for installation of cooling units with Liebert iCOM controls:
heat load in the conditioned space
cooling air distribution
number of operating units versus number of standby cooling units
location of the network switch—An Ethernet cable cannot exceed 328 feet (100m)
5.1.1 Balancing Operating and Standby Units
Assign identification to the units in a manner that balances the operating units and standby units
according to room layout and heat-load requirements. For example, identify the operating units with
numbers 1 through 5 and the standby units 6 through 10. Refer to Figure 59.
Figure 59 Standby unit layout example—10 cooling units in room
NOTE
The maximum number of cooling units that may be interconnected is 32.
Cooling units 1 through 5 are on Teamwork Rotation #1
Cooling units 6 through 10 are on Teamwork Rotation #2
Communication Cables , Teamwork Rotation #1
Communication Cables , Teamwork Rotation #2
81
2 7 36
5 9 410