Technical Specifications

ASCO Power Technologies, Florham Park, New Jersey 07932. 800-800-ASCO
www.EmersonNetworkPower.com/ASCO
8-2014 7 Publication 3279
5.1 It shall be the responsibility of the installing contractor to verify that the following items
have been completed per applicable codes and standards, and are ready to perform as
specified before the arrival of the factory technician.
A. Inspect for obvious shipping damage.
B. The equipment was properly stored (if applicable) and properly installed, anchored and
grounded.
C. Shipping splits have been reinstalled with the splits bolted together, interconnect wiring
installed, and bus splice plates installed.
D. Terminate all power cables.
E. Install customer control wiring to external equipment including engines, batteries,
building management systems, associated motor control, etc.
F. The engine generator set is installed and ready to run.
G. Associated motor controls, plumbing, building utilities are complete and operational.
5.2 It shall be the responsibility of the Factory Technician to perform the following:
A. Verify contractor connections, control power availability, visually inspect all
components.
B. With the engine generator supplier's technical representative controlling the engines,
verify that the CTTS and control equipment are fully operational, and performs as per the
specified sequence of operation. Equipment or services shall be provided by the engine
generator set supplier.
C. With the engine generator supplier's technical representative controlling the engines,
demonstrate all functions of the control system to the satisfaction of the owner or
representative.
D. Provide documentation in the form of function checklists and recorded data for each
section to the owners representative.
E. Provide plant operators with instruction on the plant operating procedures and major
component maintenance after acceptance by the owner’s representative.