User Guide
Commissioning Assistant
31-2
31.2. Monitor Pre-Power Check List
Figure 154. Monitor Pre-Power Screen (typical)
The text at the top of the Monitor Pre-Power Check List depends upon the Help (question
mark) button clicked. The screen is similar for the MPM and BDS monitors. As you complete
each item, check the box before the item. When all boxes are checked, connect to the string
by clicking the Save and Connect button. To save a partially completed check list and
connect later, click Save and Try Later.
If the string was previously commissioned, click Existing System - Ignore to connect to the
string. The remaining commissioning assistant screens will not appear.
Figure 155. Monitor Pre-Power Load Cable Help Screen
To display a table that shows the voltages between the load cables for configurations, click
the question mark on the "Verify load cable connections are made" line.