3.1 ESSENTIAL INFORMATION
Care must be taken to ensure that the dryer is not subject to flows (even peaks) in excess of the dryers
rated capacity, e.g. dryers downstream of an air receiver have increased potential to be overflowed.
The dryer can be installed free standing, secured to the floor via the fastening points provided in the
base or secured to a wall using optional brackets.
The dryer must be installed vertical and level. Suitable rated pipe and connections must be used for the
installation. All pipework must be secure and safely positioned.
The purge flow is factory set for 7 bar (100 psig) inlet pressure operation. Should the minimum
pressure requirement be dierent, the purge flow must be reset by a Airbase engineer or a Airbase
approved agent.
Ensure the dryer is electrically connected to a supply suitable for the unit.See wiring diagram printed in
2.3 Electrical Details.
ıı
ıı
Isolation Valve (outlet)
Outlet
Bypass Valve
Inlet
Isolation Valve (Inlet)
1. Filtration
A 0.01 micron coalescer and a 1 micron particle after
filter is to be installed before and after the EMD US dryer.
Filters must be maintained.
2. By-pass Line
A by-pass line ensures complete
safety during maintenance and
enables a continuous supply of
compressed air to be maintained if
required. It should be remembered
that air bypassing the dryer is dirty
untreated air.