Specification Sheet
5/16" SCREWS OR BOLTS
(12 REQ’D-NOT PROVIDED)
CHILLER SHELF
P/N 27638C
BOLT FRAMES TOGETHER
WITH 5/16" X 3/4" (19mm) BOLTS
(4 REQ’D)
HOOK RODS (2)
P/N 10-15674-43-730
SCREWS OR BOLTS
(NOT PROVIDED)
5/16" HEX NUT
(4 REQ’D)
FRAME
P/N 27049C &
P/N 27050C
37-3/4"
(959mm)
4-1/2"
(114mm)
1-1/8"
(29mm)
ELECTRICAL INLET
LOCATION ON CHILLER
TO FLOOR LINE
8"
(203mm)
BACK OF WALL
TO BE 12"
(305mm)
MIN DEPTH
5-1/8"
(130mm)
FLOOR LINE
37-1/2"
(953mm)
WOOD OR STEEL FRAME
SHOWN (NOT PROVIDED)
MAKE SURE FRAME CONFIGURATION MATCHES
THE COOLER TO BE INSTALLED
REVERSED CONFIGURATION:
HIGHER UNIT ON THE RIGHT
STANDARD CONFIGURATION:
HIGHER UNIT ON THE LEFT
1. Cut a square rectangular wall opening 37-1/2" (953mm)
W x 37-3/4" (959mm) H and 4-1/2" (114mm) above the floor
line. These dimensions are required to obtain proper
rim and bubbler heights for compliance with ANSI
standard A117.1.
2. Reinforce the wall opening on all sides so that it will
adequately support the water fountain. This reinforcement
must support up to 150 lbs. static load and provide a
means for securing the frame assembly in place.
NOTE: Building construction must allow for adequate air
flow on both sides and top of remote chiller unit. Minimum
of 4" (102mm) is required.
3. Install plumbing and electrical rough-ins. A junction box
for a (3) wire, 10 amp branch circuit is provided on the
inside of the chiller. (Standard 120 Volts, 60 Hz and single
phase)
NOTE: Reference Specification Sheet for water cooler
model to be installed for exact waste and supply locations.
4. Remove frame assembly and related hardware from
packaging. Attach the two frames together thru the upright
supports with (4) 5/16" x 3/4" (19mm) long bolts and nuts
(provided). Tighten securely. Make sure frame configura-
tion matches the cooler to be installed.
5. Install the frame assembly squarely in wall opening with
frame upright support edges flush with the finished wall
face. Secure the frame to the wall thru holes with (12) 5/16"
x 2" (51mm) bolts or screws (not provided). Tighten securely.
NOTE: Be sure that frame is squared in location. Do not use
less than required screw quantity and size.
6. Attach the chiller shelf support rods to the right side
frame uprights at the second set of holes counting from the
bottom and to the shelf at the (2) side holes. Line up the
other shelf holes with the frame bottom holes and fasten
the assembly to the wall using appropriately sized screws
or bolts and nuts (not provided).
MF200 MOUNTING FRAME INSTRUCTIONS
Two-Level Mounting Frame
Model MF200
®
ROUGH-IN DIMENSIONS
Elkay
2222 Camden Court
Oak Brook, IL 60523
www.elkayusa.com
Printed in U.S.A.
©2003 Elkay
16-21A (Rev. 12/03)