89
1
2
3
ET30000-5 ET25000-5 ET20000-5 ET15000-5 ET10000-5
Power
consumption
44KW 37KW 29KW 22KW 15KW
Overall efficiency
(typical from
-3dB to Pnom)
68% 68% 68% 68% 68%
5 Quick instructions for commissioning
5.1 Installation
If the equipment is delivered not completly assembled and/or with the connections
between individual machines not completly made , and therefore, it is necessary to
restore the structure, refer to the section “Composition” in the previous chapter.
After verifying the exact location in which to insert the modules in the rack, place these
on the brackets to the stop with the side jambs.
Lock the module with the screws provided.
It is important that :
• the equipment is located away from the room walls so that the installation and
maintenance operations can be conveniently carried out;
• the ventilation grids are not clogged;
• the equipment is far from heat sources or flammable products;
• the equipment is isolated from contact with liquids.
Elenos recommends the use of dehumidifiers at the transmitter site to reduce moistu-
re buildup in humid climates when the transmitter is turned off for extended periods.
About connections you must always give priority to the grounding cable.
For each module:
• enter phase and neutral conductors on the terminals. Secure the cables by tighte-
ning the screws with a screwdriver;
• engage RF output connectors and lock securely;
• engage RF input and signal cables into the connector.
Check that the mains voltage is appropriate.
Proceed with the connection to the electrical panel of the workstation, making
sure before that it is strictly unarmed.
In the section “Composition” in the previous chapter we report the values of most
common connections, other configurations are independently managed by other
countries.
Upon request, Elenos can supply material kits for making them.
In any case, use cables of suitable section:
Quick instructions for commissioning