Specifications

Elastic Networks 2 BitStorm 1900 Installation and Testing
08-01101-01, Rev. 1.50 BitStorm 1900 Installation and Maintenance Guide 2-119
Task 015: Testing the BitStorm 1900 Installation
Testing a BitStorm 1900 Access Multiplexer installation includes the
following tasks:
Testing voice connectivity
Testing data connectivity
End-to-end connectivity
The following sections contain testing-related information followed by
the BitStorm 1900 testing tasks. Testing tasks for network support
equipment such as LAN/WAN routers are not included in this docu-
ment.
BitStorm Access 1900™ Multiplexer Testing Locations
Primary test points for installation include the following:
Customer premise cross-connect containing the connections for the
BitStorm 1900 and customer premise equipment
Modem user locations
If the system is having trouble, other test points may be required.
Step Procedure
1.) Review the BitStorm 1900 Test Point Diagrams as follows:
Figure 2-26, "Voice/Data System Test Points," on page 120
shows the schematic layout and primary test points of a Bit-
Storm 1900 voice/data system.
Figure 2-27, "Data-only System Test Points," on page 121
shows the schematic layout and primary test points of a Bit-
Storm 1900 data-only system.