Task 015: Testing the BitStorm 1900 Installation
Testing a BitStorm 1900™ Access Multiplexer installation includes the
following tasks:
• Testing voice connectivity
• Testing data connectivity
• End-to-end connectivity
The following sections contain testing-related information followed by
the BitStorm 1900 testing tasks. Testing tasks for network support
equipment such as LAN/WAN routers are not included in this docu-
ment.
BitStorm Access 1900™ Multiplexer Testing Locations
Primary test points for installation include the following:
• Customer premise cross-connect containing the connections for the
BitStorm 1900 and customer premise equipment
• Modem user locations
If the system is having trouble, other test points may be required.
Step Procedure
1.) Review the BitStorm 1900 Test Point Diagrams as follows:
• Figure 2-26, "Voice/Data System Test Points," on page 120
shows the schematic layout and primary test points of a Bit-
Storm 1900 voice/data system.
• Figure 2-27, "Data-only System Test Points," on page 121
shows the schematic layout and primary test points of a Bit-
Storm 1900 data-only system.