INSTALLATION
POSITIONING:
Position the ACU unit in the center of the room to be conditioned if at all
possible. However, if a specific area needs to be cooled then place the unit
and the cool air outlets over these areas.
NOTE: all air inlets and all air outlets of the ACU unit must have clear space
around them and not be obstructed in anyway. For correct installation and
operation the unit must have a clearance of 0.5M from all adjacent surfaces
and or structures.
DUCTING:
The evaporator air can be directed to a desired area with the flexible ducts
provided with the ACU unit. The two flexible ducts are provided in a separate
box within the unit packaging. These ducts MUST BE FITTED to the ACU unit
BEFORE SWITCHING THE UNIT ON. To fit the ducts, remove the 8 off
fixings located on the top sloped face around the outlet cut outs. Place the
duct into position on the sloped face and then fix in place with the removed
fixings.
Ideally the condenser air outlet should be ducted out of the room / area being
cooled.
POWER SUPPLY:
Plug the unit into a suitable supply and the unit is ready for operation
If the SUPPLY CORD is damaged, it must be replaced by the manufacturer,
its service agent or similarly qualified person in order to avoid hazard.
DRAINAGE:
The ACU unit has a removable water collection container. This must be
placed into the unit before it will operate.