User's Manual
Table Of Contents
- Welcome
- Audience
- Related Documentation
- FCC Compliance Notice
- RF Statements
- EMC and Safety Statements
- Declaration of Conformity
- Introduction
- Pole Mount Installation
- Pad Mount Installation
- Introduction
- Required Tools
- Installation Location
- Preparing the Transformer Pad
- Preparing for Installation
- Performing the Installation
- Extend Pad Mounting Bracket
- Attach Pad Mounting Bracket to Lifting Nut
- Attach Conduit Housing to Pad Mounting Bracket
- Insert Conduit Thread into Conduit Housing
- Attach ECN to Pad Mounting Bracket
- Secure ECN to Pad Mounting Bracket
- Connect the ECN to Power and the Network
- Close and Lock the Conduit Housing
- Complete the Installation
- Verifying Successful Installation
- Field Replacement for an ECN 7000 Series Device
- ECN 7000 Series Specifications
- Safety and High-Voltage Warnings
- ESD and Battery Warnings
Edge Control Node 7000 Series Installation Guide 21
Figure 11. Connect the ECN to Power and the Network
Because the transformer’s lifting nut is not necessarily centered vertically with
where you placed the 1.9 cm or 3.2 cm (¾” or 1-1/4”) flexible conduit relative to
the transformer pad, ensure that the flexible conduit is long enough to reach both
the Conduit Housing and the connections on the ECN.
Close and Lock the Conduit Housing
After you have completed all cabling connections and are ready to complete ECN
installation, close the Conduit Housing door and secure it with a lock, as shown
in
Figure 12 on page 22. The Conduit Housing includes a 1.3 cm (½ inch) hasp
hole for the lock.