4-68. PURGING TANK (Con't).
(24) Even if semitrailer has tested
SAFE with combustible gas indi-
cator set, it must be retested
prior to starting work each day
and at regular intervals through-
out the day.
(25) If removed,
install emergency
valve (9) (see paragraph 4-82). If
removed,
install nut (10) to
bleeder valve.
CAUTION
Purging introduces water into semitrailer’s bottom loading system. Win-
terization is needed to prevent freezing and damage to bottom loading sys-
tem. If freeze-up occurs, semitrailer will not bottom load.
(26) After work is complete, and before loading fuel or shipping, winterize bottom loading system
(see paragraph 4-84).
(27) Install dust caps to rear roadside vapor collection adapter (4) and front port (1). Close rear
inlet (3) cover and butterfly valve (2). Push on sump drain control lever (7) to close tank
sump (8).
(28) Install ¼ in. (6.4 mm) center plug in strainer assembly (see paragraph 1-15).
4-211