User`s guide

VERSION 1 TIE CABINET PARALLEL INSTALLATION
Eaton 9355 Parallel UPS (10/15 kVA) User's Guide S 164201601 Rev B www.eaton.com/powerquality
19
7. Punch holes for the conduit (AC input, UPS output, load connection,
and maintenance bypass contact wires) using a Greenlee
®
punch or
similar device.
8. Verify that the parallel bypass breaker is in the OFF position (see
Figure 13).
9. Mount the parallel tie cabinet to the wall and install the conduit.
Figure 13. Version 1 Parallel Bypass Breaker
10. Verify that each UPS battery circuit breaker is in the OFF position
(see Figure 14).
11. From each UPS, remove the UPS wiring access cover and one of
the conduit landing plates and retain.
12. Punch two holes in the conduit landing plate for the input and
output conduit using a Greenlee punch or similar device.