Step 3 - Set up SC200 or SC100
Configure the inputs and outputs after completing the installation and all the Startup
Tasks on page 36.
For configuration details refer to Digital Inputs and Digital Outputs in the System
Controller Operation Handbook (see Related Information on page i).
Step 4 - Refit top cover (if removed)
Replace the top cover (if fitted and all installation tasks are completed).
Procedure complete
Task 9 - Connect Additional Input/Output (if required - SC200 only)
If additional input/outputs are required then SiteSure-3G modules can be connected to the APS
(SC200 only). A SiteSure-3G input/output module has the following features.
SiteSure-3G
Digital Inputs
10
Digital Outputs (relays)
6
Analog Inputs (0 to 10V)
4
Current Sense Inputs
3
Temperature Sense Inputs
2
Bus Voltage Input (0-60V)
1
Enclosure
Wall or panel mounting plastic case
For further information refer to the SiteSure-3G Installation and Operation Guide (see Related
information on page i).
Connect the SiteSure-3G cable to a spare RJ45 socket (S1, S2 or S3) on the Voltage Feed Module
board. See the diagram on page 3 (APS6 models) or the diagram on page 6 (APS12 models) for
socket location.
Task 10 - Connect to the AC Supply Point

A suitably qualified electrician familiar with local wiring regulations must carry out the ac
connection.
Step 1 - Replace all covers on the APS