Specifications
Access Power Solutions Installation and Operation Guide (APS6-300/500 and APS12-300 Series)
20
Copyright © 2007-2012 Eaton Corporation. All Rights Reserved.
IPN 997-00012-49F November 2012
Installation Tasks
Before starting the installation, review the following information:
Required Equipment and Tools on page 69
Warnings and Cautions on page 16
Inspecting the Equipment and Reporting Damage on page 18
Complete the Installation tasks in the following order:
Task
Description
Reference
1
Check the AC Supply and Earthing
See details on page 20
2
Prepare the APS
See details on page 23
3
Connect the AC Supply Cable
See details on page 26
4
Mount the APS in the Rack
See details on page 28
5
Connect the dc Load and Battery Cables
See details on page 29
6
Install the Batteries
See details on page 30
7
Mount the Battery Temperature Sensor
See details on page 31
8
Connect External Input/Output Cabling (if required)
See details on page 32
9
Connect Additional Input/Output (if required - SC200
only)
See details on page 33
10
Connect to the AC Supply Point
See details on page 33
For installation of external communications see Communications Options in the System
Controller Operation Handbook.
Task 1 - Check the AC Supply and Earthing
It is important that the ac supply for the Access Power Solutions dc power system includes the
correct levels of protection.
Step 1 - Check transient voltage protection at the site
1 Confirm that there is a transient protection plan (compliant with IEC 61643-12)
for the site.
For more information see Transient Protection on page 87.
2 If necessary, install suitable transient protection.