A p p e n d i x H
Commissioning
Complete the tasks in this appendix only if a formal commissioning test is required.
Before starting these Commissioning tasks:
Complete all the Installation tasks (see details on page 20)
Complete all the Start-Up tasks (see details on page 36)
Save a copy of the configuration file.
Complete the Commissioning tasks in the following order:
During the testing, note any changes to the configuration file that are incorrect.
Task
Description
Reference
1
Analog Inputs
See details on page 94
2
System Controls
See details on page 96
3
System Alarms
See details on page 99
4
Digital Inputs
See details on page 102
5
Digital Outputs (Relays)
See details on page 103