3BUS 208 000 R1301 41Hardware Installation
14. Carefully lift the Scanning Platform from the transporting skid or dolly and
position it on the customer pedestals so that the platform and the support
structure mounting holes are aligned.
The mounting holes center–to–center dimension should be within 0.125 in. (3
mm) of the dimension noted on the dimensional outline drawing. The
dimensional drawing is site specific.
15. Install four customer-provided hold-down mounting bolts, leaving them loose
enough for Scanning Platform alignment later.
The platform is now in position.
16. Rethread the two parallel lengths of wire over the rolls onto which the process
is guided. See Figure 3-7 on page 39.
17. Verify that the wire locations represent the outside edges of the process sheet.
18. Separate the head assembly.
19. Manually move the lower carriage assembly close to the wire at one end of the
platform.
20. Adjust the jackscrews in the base of the applicable column to position the wire
at the center of the source detector air gap. See Figure 3-6 on page 38 and
Figure 3-8 on page 40.
21. Move the carriage assembly to the other end of the Scanning Platform.
22. Adjust the front jackscrews to position the wire in the center of the source
detector air gap.
23. At the idler end of the platform, compress the lock washer approximately half–
way.
24. At the drive end of the platform, tighten the screws securely.
25. Verify that there is approximately equal travel remaining in each direction in
the slotted holes in the idler end pedestal.
This completes the preliminary installation of the Scanning Platform.