Installation Sheet
- 2 -
M965701 Rev. 1.1 (5/17)
1
2
INSTALL VALVE BODY
• Mount VALVE BODY (1) to WALL BRACKET (2) as shown. Level and tighten SET SCREWS (3) to secure 
VALVE BODY (1) to WALL BRACKET (2).
• Connect HOT water supply to LEFT INLET UNION (4) and COLD water supply to RIGHT INLET UNION (5). 
Pipe connections are 1/2" NPT. Use sealant or Teon tape on pipe connections. Do not solder directly to valve body.
• With valves closed open supply lines and check for leaks. Remove PLASTER GUARDS (6) and open both 
valves and check for leaks.
• Close both valves and turn off water supplies. Replace PLASTER GUARDS (6) and nish wall construction.
• Determine where the nished wall location will be. This measurement is very important! Note: The rough-in measurement 
from the nished wall is; 1-9/16" (40 mm) minimum and 2-7/16" (62 mm) maximum. This is a 7/8" (22 mm) tolerance.  
See rough-in illustration above.
• Secure WALL BRACKET (1) to cross brace of wall structure at required height using six wood screws.
INSTALL WALL BRACKET
WOOD SCREWS
CROSS BRACE
WALL STUDS
1 
16" (406 mm)
HOT
COLD
6 
6 
5 
4 
2 
1 
3 




