COMMISSIONING CHECK LIST
1. The Airoheat produces water condensation so make sure the unit is
installed on a flat surface, and ensure you install a condensate drain
from the condensate drain port down the side of the water heater.
2. Tempering Valves are a requirement, ensure you commission them
correctly; incorrect commissioning leads to lack of hot water delivery.
3. Make sure the all copper pipes are lagged with high temperature
closed cell 13mm minimum insulation.
4. Ensure no obstruction on top of the Airoheat; it will block the air outlet.
5. Check that there are no faults when the system is turned on, check the
Hotlogic (inside top cover you can access from top of Airoheat) status
lights to help you determine if there is a fault.
6. Check the refrigerant sight glass disk located in the top cover of the
unit, that the colour is green not yellow, if yellow do not turn on the
Airoheat contact Dux Hot Water