Instructions / Assembly
5
b. Place the exterior grade CDX 3/4” (19mm.)
plywood on top of the foundation. (Plywood not
included.)
Plywood should be place after
completing the side panel
assembly
.
Note
9. Place the ramp (RG) to the front side of the
foundation and keep the distance according to the
wheel distance. Use dia. 2.5mm. drill bit to transfer
the hole from
(RG) and fix with (S1) screws.
Filler Material and Flooring Recommendation
OPTION - 1.
Gravel Floor with Plywood
a.
After completing the assembly of the base U-
channel fill the gravel up to the foundation top
surface only.
Fill the concrete inside the ramp only
.
Concrete
Gravel
Ramp
RG
RG
S1
1220mm.
1865mm.
2238mm.
765mm.
627mm.
1220mm.
683mm.