Installation Instructions
Start at the bottom of the structure to ensure proper shingling throughout the 
installation. Proper shingling is required to shed water and to prevent water from 
entering the wall system.
STEP 1
UNWRAP roll at corner, leaving 6” to 12” vertical overlap.
Printed stud marks are available on some DuPont
™
 Tyvek
®
 WRBs to aid in aligning with 
the studs. (e.g. studmarks are 8” apart for DuPont
™
 Tyvek
®
 HomeWrap
®
)
STEP 2
Roll should be plumb. Bottom edge of roll should extend over sill plate interface at least 
2”. For maximum air leakage reduction (when installing as an air barrier), seal wrap at 
the bottom of the wall with sealant (i.e. DuPont
™
 Residential, DuPont
™ 
Commercial 
Sealant or recommended sealant), DuPont
™
 Tyvek
®
 Tape, DuPont
™
 StraightFlash
™
 or 
DuPont
™
 Flashing Tape. Extend to bottom of sill plate for slab on grade foundations. For 
stucco exteriors integrate with weep screed.
STEP 3
Secure DuPont
™
 Tyvek
®
 WRB to the stud or other nail-base material i.e wood sheathing. 
Fasteners should be spaced no closer than 6” and no farther than 18” on vertical stud 
lines. This may involve penetrating bandboard or other horizontal members to maintain 
proper spacing. Use one or more of the recommended fasteners below for use with 
DuPont
™
 Tyvek
®
WRBs:
• DuPont
™
 Tyvek
®
 Wrap Cap nails 
• DuPont
™
 Tyvek
®
 Wrap Cap screws 
• DuPont
™
 Tyvek
®
 Wrap Cap Staples for Stinger™* 
• 1.0inchminimumcrownstaples*
*Except when installing DuPont
™
 Tyvek
®
 WRB over foam and other non-nail-base 
sheathings.
Please see “Use of Temporary Fastening Methods” later in this guide for more 
information on alternative fastening schedules and requirements. 
NOTE: Do not fasten within 9” of rough opening head.
STEP 4
Unroll directly over windows and doors. Upper layer of DuPont
™
 Tyvek
®
 WRB should 
overlap bottom layer by a minimum of 6”.
Refer to the DuPont
™
FlashingSystemsInstallationGuidelinestoprepareandash
window and door openings.
NOTE: If windows are already installed, the DuPont
™
 Tyvek
®
 WRB must be integrated 
withpropershinglingwithwindowashings.IfDuPont
™
 FlexWrap
™
 NF and apron are 
used, install the DuPont
™
 Tyvek
®
 WRB under the apron to ensure proper shingling. If 
non-selfadheringsillashingisused,installtheWRBunderthebottomofthesill
ashingtomaintainpropershingling.
STEP 5
All vertical seams shall be 
taped with DuPont
™
Tyvek
®
 Tape. When 
installing as an air barrier, 
also tape all horizontal 
seams. Taping all vertical 
and horizontal seams, and 
taping or sealing all 
terminations (including, 
but not limited to, 
roof-wall interfaces and 
sill plates) is required 
when installing DuPont
™
Tyvek
®
 WRBs as air 
barriers. Use 3” DuPont
™
Tyvek
®
 Tape when taping 
horizontal laps of DuPont
™
Tyvek
®
 StuccoWrap
®
 and 
DuPont
™
 Tyvek
®
DrainWrap
™
. Use DuPont
™
Tyvek
®
 Metalized Tape 
when taping DuPont
™
Tyvek
®
 ThermaWrap
™
.
STEP 6
After DuPont
™
 Tyvek
®
WRB is installed refer to 
the DuPont
™
 Flashing 
Systems Installation 
Guidelines, Installation 
Instructions for Windows 
and Doors AFTER 
Water-Resistive Barrier 
(WRB) is Installed to 
prepareandash
windows and doors.