Specifications

11
VAPORMIST INSTALLATION, OPERATION, AND MAINTENANCE MANUAL
Piping:
INSTALLATION
Unions by installer
Strainer, by installer
3/4" pipe thread (DN20) tank
drain, and P-trap piping, rated
for 212 °F (100 °C). If piping
run is over 10' (3 m) increase
pipe to 1¼" (DN32) after P-trap.
1" (25 mm) air gap
Spill funnel. Plumb
to floor drain
Frame drain
Cover
Install plumb
DC-1139
First 3' (1 m) of water supply line
should be stainless steel tubing with
a 2" (50 mm) water seal or loop in
the supply line to isolate steam from
nonmetallic supply piping.
2" (50 mm)
12" (300 mm)
Notes:
Locate air gap only in spaces with adequate temperature and air movement to absorb flash steam; otherwise, condensation may form on nearby
surfaces. Refer to governing codes for drain pipe size and maximum discharge water temperature.
Offset humidifier from spill funnel or floor drain to prevent flash steam from rising into the cabinet.
Dashed lines indicate provided by installer.
The water supply inlet is more than 1" (25 mm) above the overflow port, eliminating the possibility of backflow or siphoning from the tank. No
additional backflow prevention is required; however, governing codes prevail.
Install a union in the water supply and drain lines as shown to allow tank removal.
Damage caused by chloride corrosion is not covered by your DriSteem warranty.
Open drain required.
See first note below.
3/4" pipe thread (DN20) frame drain
and P-trap piping, rated for 212 °F
(100 °C)
Steam hose (maximum run 10' [3 m]). May also use tubing.
See the DriSteem Design Guide for maximum tubing lengths.
mc_042710_1328-VM
Water supply line:
¼" NPT (DN8) connection size
25 to 80 psi (175 to 550 kPa)
required water pressure.
RO/DI water option
FIGURE 11-1: VAPORMIST (RO/DI WATER OPTION) FIELD PIPING OVERVIEW