Specifications
20
RAPID-SORB
®
ASSEMBLY AND INSTALLATION
Figure 20-3: Elevation View
Tube with Drain
Figure 20-1: Plan View
Steam
Supply
1/8" per foot
pitch minimum
Drain
5" Min.
6" Min.
Recommended 2" per
foot pitch
Figure 20-2: Elevation View
Tube without Drain
Recommended 1/4"
per foot pitch
Airflow
1/4" NPT
Condensate Drain
5" Min.
6" Min.
3/4" NPT Coupling
5" Min.
Open Drain
Airflow
ULTRA-SORB
®
INSTALLATION
See the ULTRA-SORB Installation Instructions and
Maintenance Operation Manual.
Vertical Duct Installation
Install the RAPID-SORB with dispersion tubes and header
pitched to condensate drain as shown in figures 20-1,
20-2, and 20-3.
See "Instructions for Horizontal Duct" for additional
information, as applicable.
OM-700
Piping (by others)
GTS-IOM-1298.pdf 20 11/17/2009 3:57:05 PM