COMMISSIONING
It is a requirement of the Supply of Machinery (Safety) Regulations
1992 to provide adequate isolation and emergency stop facilities. Due
to the varied nature of site installations this cannot be provided by
Donaldson but instead is the responsibility of the customer.
Commissioning check list
Ensure the dust collector is securely bolted over the aperture.
Open the access door(s) and ensure the seal is intact, then close and secure
the door(s).
Ensure controller is connected to the correct voltage and that the pulse
interval and duration settings are correct. For 24V DC ensure polarity is
correct. It is essential that the controller is earthed for both AC and DC
connections.
Ensure electric power is available.
Ensure the compressed air manifold has sufficient protection for over-
pressure.
Start the compressor and check that the air supply is maintained at the
recommended pressure.
Switch on the controller and check that all valves operate in sequence (look
and listen for exhaust pulses). As each valve operates, the air pressure
reading should drop to approximately 50% of the initial setting and then
return to the initial value.
If any of the above check boxes are not ticked, then the reasons why should be
investigated. (Refer to fault location table in ‘Maintenance’ section).
Start-up sequence
Having completed all the necessary checks, the equipment may be put into
operation. A typical installation should be started up as follows:
1 Start up compressed air supply.
2 Set the equipment being served, if applicable, in motion.
3 Switch on controller.