    Dobot M1 User Guide  6 Operation 
Issue V1.0.4 (2018-08-30)  User Guide  Copyright © Yuejiang Technology Co., Ltd 
  78   
  Input command M415 on the lower right of the Operational page to save the 
printing coordinates, as shown in Figure 6.29. 
Figure 6.29 Input command M415 
NOTICE 
If the yellow LED indicator is always on when printing, the connection between Dobot 
M1 and 3D printing kit is poor. Please check the connection and restart Dobot M1. 
  Operating I/O Assistant   
Prerequisites 
  Dobot M1 has been powered on. 
  Dobot M1 has been connected to the PC successfully. 
  Dobot M1 has been connected to the emergency stop switch. 
  The air pump has been installed (If you use air pump to debug I/O interface). 
Application Scenario 
The end effectors such as gripper, suction cup need to work with the air pump. The air pump 
can be controlled by the I/O interface. You can verify the I/O interface and the air pump over I/O 
Assistant.   
Procedure 
If the air pump is connected to the base I/O interface, the outputs used are DOUT17, DOUT18 
respectively.  For  details,  please  see  3.4  (Optional)  Installing  Air  Pump.  The  DOUT18  output 
controls the startup and shutoff of the air pump. 
The I/O Assistant page is displayed. 