Specifications

Confidential Page 35
Equipment Racks/Assembly
Install all equipment and shelves in the proper locations as specified in plans
provided by DMX.
Tighten all rack rail bolts to insure rail stability.
Install rear supports for deep or heavy equipment.
Install Panduit or other raceway for wire management, if needed
Install lacing bars for wire support to equipment if needed
If multiple racks, connect all racks with a common ground of at least 14 awg. to
prevent floating rack ground.
If fans are required, utilize the provided cut out in the top of racks to save rails
for equipment.
Provide grommet stripping on all knockouts used as cable entry to prevent cable
scarring.
Place plans and ‘as built’ wiring diagram in pouch provided by DMX and attach
to inside of rack to facilitate service work.
Separate all cables by 6” in groups as follows:
Mic Level Nothing to -20dBm REF. (.775mV @ 600 Ohms)
Line Level -20dBm to +30dBm
Speaker Level +30dBm and up
Video RF Cable, DMX Satellite Cable, Control, Ethernet
All equipment racks must have a minimum wiring service loop of 5’ to facilitate
servicing or changes to system.
Edited 09-23-2010