Technical data

SOLC220 - Free standing kit
Page 17 of 20
ST0117 – C 08/09
SOLAR
Step 2.7.5 Collector
- Preassemble the lower T-pieces to the
U-pieces using M10 hexagonal bolts
(3.6), large spacer sleeves (3.9),
spring washers (3.7) and M10 hexago-
nal nuts (3.8).
- Keep supporting the collector until all
M10 hexagonal bolts have been at-
tached.
- Screw tight all M10 hexagonal bolts
with spring washers and M10 hexago-
nal nuts.
Step 3.1 Connections
The remaining interconnections are
made, ensuring that;
- Insert rings (6.2) are placed in the 4
th
and 5
th
trough of the corrugated pipe
(6.1), counted from the end, on the
side faced next to the collector.
- The insert rings must be securely
pressed around the circumference of
the corrugated pipe.
- Next insert the corrugated pipe (6.1)
until blocked by the 1st insert ring.
Ste
p
3.2 Connections
- Pull clamps (6.3) over the collector
connections and the outer insert rings,
then press with adjustable pliers or
grips and fix it using the screw.
- Make sure that the outer insert ring is
completely covered by the clamp.